As early as the 1960s,
officials identified the US 93 route over Hoover Dam to be dangerous and
inadequate for projected traffic volumes. From 1998–2001, officials from
Arizona, Nevada, and several federal government agencies collaborated to
determine the best routing for an alternative river crossing. In March 2001, the
Federal Highway Administration selected the route, which crosses the Colorado
River approximately 1,500 feet (460 m) downstream of Hoover Dam.
Construction of the bridge approaches began in 2003, and construction of the
bridge itself began in February 2005. The bridge was completed in 2010 and the
entire bypass route opened to vehicle traffic on October 19, 2010.
The bridge was the first
concrete-steel composite arch bridge built in the United States, and it
incorporates the widest concrete arch in the Western Hemisphere. At 840 feet
(260 m) above the Colorado River, it is the second-highest bridge in the United
States, following the Royal Gorge Bridge. It is also the world's highest
concrete arch bridge. The Hoover Dam Bypass project was completed within budget
at a cost of $240 million; the bridge portion cost $114 million (2010 prices).
In
1935, the American Association of State Highway Officials (AASHO, later AASHTO)
authorized a southward extension of U.S. Route 93 from its previous southern terminus in Glendale,
Nevada to Kingman, Arizona by way of Las Vegas and Boulder City, crossing the Colorado
River on the newly-constructed Hoover Dam (also known then as Boulder Dam). At
the time, Clark County, which now has a population of nearly 2 million, was
sparsely populated, with a population of less than 9,000 at the 1930 U.S.
Census. Development in and around Las Vegas in the latter half of the 20th
century made Las Vegas and its surrounding area a tourist attraction, and US 93
became an important transportation corridor for passenger and commercial
traffic between Las Vegas and Phoenix. In 1995, the portion of US 93 over
Hoover Dam was included as part of the CANAMEX Corridor, a high-priority
transportation corridor established under the North American Free Trade
Agreement (NAFTA). This bridge is a key component of the proposed Interstate 11
project.
Through
traffic on US 93 combined with pedestrian and tourist traffic at Hoover Dam
itself led to major traffic congestion on the dam and on the approaches to the
dam. The approaches featured hairpin turns on both the Nevada and Arizona sides
of the dam, and the terrain caused limited sight distances around curves. In
addition to traffic safety considerations, officials were also concerned about
the safety and security of Hoover Dam, specifically the impact a vehicle
accident could have on the dam's operation and the waters of Lake Mead.
Officials first. The U.S. Bureau of Reclamation, which operates the dam, began
work on the "Colorado River Bridge Project" in 1989, but the project
was put on hold in 1995. In 1997 the Federal Highway Administration took over
the project and released a draft environmental impact statement in 1998. From
1998–2001 state officials from Arizona and Nevada as well as several federal
government agencies studied the feasibility of several alternative routes and
river crossings, as well as the feasibility of modifying the roadway over the
dam, restricting traffic over the dam, or doing nothing.
In
March 2001 the Federal Highway Administration issued a Record of Decision
indicating its selection of the "Sugarloaf Mountain Alternative"
routing. The project called for approximately 2.2 miles (3.5 km) of
highway in Nevada, 1.1 miles (1.8 km) of highway in Arizona, and a 1,900-foot
(580 m) bridge that would cross the river 1,500 feet (460 m)
downstream (south) of Hoover Dam. Design work began in July 2001. Security
measures implemented following the September 11 attacks prohibited commercial
truck traffic from driving across Hoover Dam; commercial vehicles were required
to follow a 23-mile (37 km) detour to a river crossing between Laughlin,
Nevada and Bullhead City, Arizona.
Design
Project
design was by the Hoover Support team, led by HDR, Inc. and including T.Y. Lin
International, Sverdrup Civil, Inc., and other specialist contributors.
The
bridge has a length of 1,900 feet (579 m) and a 1,060 ft (320 m)
span. The roadway is 900 ft (270 m) above the Colorado River and four
lanes wide. This is the first concrete-and-steel composite arch bridge built in
the United States. It includes the widest concrete arch in the Western
Hemisphere and is also the second highest bridge in the nation, with the arch
840 ft (260 m) above the river. The twin arch ribs are connected by
steel struts.
The
composite design, using concrete for the arch and columns with steel construction
for the roadway deck, was selected for schedule and cost control while being
aesthetically compatible with the Hoover Dam. Sean Holstege in The Arizona
Republic has called the bridge "an American triumph”. USA Today called it
"America's Newest Wonder" on October 18, 2010.
Pedestrian
access is provided over the bridge to tourists who wish to take in a different
view of the nearby dam and river below, but the dam is not visible for those
driving across it. A parking area is provided near the bridge on the Nevada
side at what was a staging area during construction. A set of stairs and disabled
access ramps lead to the sidewalk across the bridge.
Construction
Work
began in 2003 on the approaches in both states and the construction
contract for the arch bridge was awarded in October 2004. The largest obstacle
to the project was the river crossing. The bridge and the bypass were
constructed by a consortium of different government agencies and contractors,
among them the Federal Highway Administration, the Arizona Department of
Transportation, and Nevada Department of Transportation, with RE Monks
Construction and Vastco, Inc, constructing the Arizona Approach, Edward Kraemer
& Sons, Inc, the Nevada Approach and Las Vegas Paving Corporation
undertaking the roadway surfacing on both approaches. The bridge itself was
built by Obayashi Corporation and PSM Construction USA, Inc., while Frehner
Construction Company, Inc. was responsible for completing the final roadway
installations. A permit problem between Clark County and the subcontractor Casino
Ready Mix arose in May 2006 over the operation of a concrete-batch plant for
the project, and this caused a four-month delay.
Construction
required hoisting workers and up to 50 short tons (45 t) of materials 890
feet (270 m) above the Colorado River using 2,300 ft
(700 m)-long steel cables held aloft by a "high-line" crane
system. High winds caused a cableway failure in September 2006, resulting in a
further two-year delay. The approach spans, consisting of seven pairs of
concrete columns—five on the Nevada side and two on the Arizona side—were
completed in March 2008. In November 2008, construction worker Sherman Jones
died in an accident.
The
arches are made of 106 pieces—53 per arch—mostly 24 ft (7.3 m) cast
in place sections. The arch was constructed from both sides of the bridge
concurrently, supported by diagonal cable stays strung from temporary towers.
The twin arch spans were completed with the casting of the center segments in
August 2009. That same month, the two halves of the arch were completed, and
were 3⁄8 inches (9.5 mm) apart; the gap was filled
with a block of reinforced concrete. The temporary cable stays were removed,
leaving the arch self-supporting. By December, all eight of the vertical piers
on the arch had been set and capped, and at the end of the month the first two
of thirty-six 50-short-ton (45 t) steel girders had been set into place.
By
mid-April 2010, all of the girders were set in place, and for the first time
construction crews could walk across the structure from Arizona to Nevada.
Shortly thereafter, the pouring of the bridge deck began. The bridge deck was
fully paved in July, and the high-line cranes were removed from the site as the
overall project neared completion The Bridge was completed with a dedication
ceremony on October
14, 2010. and a grand opening party on October 16. It was opened to
bicycle and pedestrian traffic on October 18 and to vehicular traffic on
October 19, a
few weeks earlier than estimated. The building of the bridge was featured in
episode 5x02 of the TV series Extreme Engineering. The filming of this episode
took place before the start of work on the arch.
When
the bridge opened to traffic, the roadway over Hoover Dam was closed to through
traffic, and all visitor access to the dam was routed to the Nevada side;
vehicles are still allowed to drive across the dam to the Arizona side
following a security inspection, but must return to the Nevada side to return
to US 93 The former US 93 route between the dam and its junction with the
present US 93 route has been re-designated as Nevada State Route 172.
No comments:
Post a Comment